JSW with loan for battery-powered locomotives

Eight VOLTER overhead battery-powered locomotives with complete transport sets have been delivered to the Budryk mine in Ornontowice. The investment was made thanks to a PLN 9.96 million loan from the Voivodeship Fund for Environmental Protection and Water Management in Katowice.

photo: Marcel Kleczka

Transportation at the Budryk mine is mainly based on suspended cable cars. Six newly purchased locomotives are used to transport input materials to the working face in areas of excavated roadways.

The other two locomotives are used to keep the main coal haulage moving from the 1050 level to the 700 level, as well as from the 1290 level to the 1050 level. The locomotives transport, among other things: belt conveyor construction elements, and pipes for fire protection, compressed air, drainage and air conditioning pipelines.

The purpose of using this type of locomotive is to improve air quality and reduce energy consumption. It is worth noting that the Voivodeship Fund for Environmental Protection and Water Management in Katowice has granted funding for this purpose in the form of a loan which can be partially written off after a few years. The value of the entire project is PLN 12.38 million.

Other news

Stable production and sales growth despite difficult market conditions

Jastrzębska Spółka Węglowa has published its operating results for October 2025, which indicate stable production and a significant increase in sales, particularly in the steam coal segment. Despite difficult market conditions and unforeseen circumstances, the Company…

The final of the 13th edition of the OHS competition resolved

The 13th edition of the Competition on knowledge of OHS rules and regulations for the Cup of the JSW SA President took place at the Pniówek mine. The winner of the individual competition was Rafał Gembalczyk from the Borynia Section.

JSW is preparing a restructuring plan. Estimated production in 2026 will amount to approx. 13.5 million tons.

Jastrzębska Spółka Węglowa S.A. is preparing a business restructuring plan. Analyses conducted in the area of production and sales indicate that in 2026 the Company plans to extract approximately 13.5 million tons of coal.

JSW continues work on business restructuring plan

Jastrzębska Spółka Węglowa SA is working on a comprehensive business restructuring plan aimed at increasing the Company's efficiency, competitiveness and organizational flexibility.

JSW acquires JSW Nowe Projekty

On 22 October 2025 the Management Board of Jastrzębska Spółka Węglowa S.A passed a resolution on adopting the Plan of Merger between JSW SA and its subsidiary, JSW Nowe Projekty SA, and a resolution on applying to the JSW SA Supervisory Board for an opinion on the…

Talks with the trade unions are underway

JSW S.A. hereby reports that on 16 October another meeting was held with representatives of representative trade union organizations operating in the Company. Its purpose was to try to work out a framework for agreement on adjusting labor costs to the Company's current…

More news