The most difficult stage of deepening shaft III at KWK Pniówek has been completed

Work on the deepening of the material transport shaft at the Pniówek mine has reached a key stage. Shaft III has been deepened to the target depth of 1,053 meters. The implementation of the project is an important step in the modernization of the mine's infrastructure, providing new development opportunities and improving working conditions.

photos: Dawid Lach

Deepening of the shaft from a depth of 865.3 meters began in July 2020 after completion of preparatory works. As regards the deepening of Shaft III, 187.7 meters of the shaft in the final casing have been completed, along with one-sided inlets at the depths of 965.4 meters and 1,052 meters, and a two-sided inlet at the 1,000-meter level. 

- The investment will enable efficient transport of materials and workers to the 1,000m level, which will significantly improve logistics and ventilation of the pits - said Zbigniew Czarnecki, director of the KWK Pniówek mine.

On 19 November, a ceremony was held at the bottom of Shaft III, during which the mine director received official confirmation of the completion of the task. 

- This project, which has been ongoing for several years, was one of the most important tasks in Pniówek. The most difficult stage - deepening the shaft - has been completed, and work is currently underway to reinforce the shaft pipe on the deepened section - said Adam Rozmus, JSW's Vice-President for Technical and Operational Matters.

The project is being carried out by a consortium of companies: Przedsiębiorstwo Budowy Szybów from the JSW Group and PPG Row-Jas.
 

Other news

The JSW Management Board has asked the Company’s trade unions to select joint representatives to work out a salary agreement

Jastrzębska Spółka Węglowa S.A. has sent a request to all 82 trade union organizations operating in the Company to select joint trade union representation and to respond to a draft agreement concerning the temporary suspension of selected payroll benefits.

Cooling for the entire mine

Three technological halls, closed-loop water circulation, and an oil-fired boiler room as a backup heat source. These are the features of the air conditioning station which will provide cooling for the Knurów mine workings in the coming months. The performance of the…

Open letter to Representative Trade Union Organizations operating at JSW SA

Dear Sirs/Madams,

On Tuesday, 30 December, another round of talks took place. Unfortunately, it has still not been possible to reach an agreement between the Management Board and the trade unions. We strongly urge you once again to be open to reaching a compromise and…

Talks between the JSW SA Management Board and the trade unions without agreement

(UPTADE) The talks between the JSW SA Management Board and the trade unions concerning the need to temporarily reduce labor costs in the Company ended without reaching an agreement. The JSW SA Management Board remains determined to continue the dialogue and work out…

Rescue operation in KWK Pniówek completed

(UPDATE) After seven hours of rescue efforts, rescue workers reached two missing miners with whom contact had been lost after a methane leak in the N-9 working face at a depth of 830 meters. Unfortunately, the doctor pronounced them dead. Both miners were experienced…

Strategic investment in Pniówek completed

December saw the completion of one of the most important investments in the history of the Pniówek mine. The deepening of Shaft III to a depth of 1,053 meters and the commissioning of the new level 1,000 is a landmark stage in improving safety, transport efficiency and…

More news