Ikona BIP Ikona Portal Pracownika Ikona poczty Facebook Twitter Instagram Youtube Linkedin RSS Ikona szukania PLEN

Refurbishment of supports pays off

The Pniówek mine has invested in a new material refurbishment chamber. In the chamber the steel that was to be scrapped is being recovered and reused. The technologically advanced machine, during one day, makes it possible to refurbish approx. 420 running meters of gallery supports with a total weight of 13,440 kg.

photo: Dawid Lach

The new recycled material refurbishment chamber has been built on level 1000 at the site of a former sedimentation tank. 


“We carried out the adaptation of this site to new uses with the in-house work system, using the knowledge and experience of the mine's employees,” says Marcin Mikołajczyk, Technical Director of KWK Pniówek. 

The project was launched in October 2022. In the first stage, the walls were demolished and the infrastructure of the old sedimentation tank was removed. Next, a shaft sink channel was made for the bending and straightening machine, so that maintenance work can be carried out and components protecting the machine from overloading can be replaced. The machine is founded on a reinforced concrete slab. The entire 80-meter-long refurbishment chamber was reinforced with steel beams, and a 15 meter section was covered with sprayed concrete. The chamber along its entire length is illuminated and whitewashed, and the floor is covered with poured concrete. The work was completed by installation of a transport system based on a shunting tractor with hydraulic winches. After the installation of the ODP-6 bending and straightening machine and workbenches in April 2023, successful operational tests and the necessary approvals were carried out with the participation of the machine manufacturer. After that the material refurbishment chamber has started working. 

“The ODP-6 bending and straightening machine is a high-tech machine. Straightening of the support elements is carried out by rolling, which restores them to an almost perfect shape. Such a good end result of the refurbishment was not achievable in other machines used so far. The high quality of the strength parameters of the obtained steel support straights has been confirmed by tests of the GIG Research Institute. This is a new quality in the support straightening process at the Pniówek mine,” explains Sebastian Derbis, manager of underground mining operations at KWK Pniówek.

Currently, work in the chamber is carried out in 3 shifts. Each shift is capable of refurbishing 40 support elements with a V32 profile and a length of 3.5 meters, allowing 420 running meters of supports to be refurbished per day. The weight of one running meter of V32-profile supports is 32 kg, so the total weight of supports refurbished in a day is 13,440 kg. The net purchase price of 1 running meter of a new support at the current price level is PLN 131.84, and the net price of scrap metal sold by the mine to the smelter is PLN 1.28 per kg. Thus, from 1 sunning meter of scrap support sold, the mine recovers 40.96 PLN net from selling the scrap. Comparing the scale of profitability of selling scrap supports to its refurbishment at a recovery level of 420 running meters per day, the mine gains PLN 38,169.60 in savings per day, excluding labor costs. After labor costs, the mine gains PLN 30,690.60 in savings per day, without further reducing the capacity and operation of the shaft. Under these assumptions, the purchase of the innovative machine will pay off already after 6 months of operation.

“The new chamber doesn't just straighten the supports. Here, we also refurbish the fastening clamps for connecting the ŁKWH V29 and V32 supports, SD V29 and V32 connectors, sprags for the supports, slings for suspended cable cars, structures, belt conveyor rollers and many other small components,” says Mariusz Bujok, shift foreman of the material and support refurbishment department, adding: “With a view to achieving the highest possible efficiency of the work carried out in the material refurbishment chamber, all workstations have been equipped with a pneumatic wrench, and transport and loading and unloading work is carried out using a shunting tractor equipped with hydraulic hoist equipment. 

The Pniówek mine, through a carefully considered investment in a technologically innovative and comprehensively equipped chamber for the refurbishment of gallery supports in underground workings, has become a leader among Polish mines. Currently, the refurbishment chamber is attracting a lot of interest from mining companies from all over the region, and the Pniówek mine is eager to share the experience gained.

 

The material refurbishment chamber at the Pniówek mine is located on level 1000.
A support arch to be refurbished is manually laid on a roller table and then placed in the pulling set of the ODP-6 bending and straightening machine.
Straightening of the support elements is carried out by rolling, which restores them to an almost perfect shape.
The operator of the bending and straightening machine performs the support straightening process.
A refurbished support is manually slid onto a trestle.
Mariusz Bujok, a shift foreman from the material and support refurbishment department at the shunting tractor with which the refurbished support elements are loaded into a rail transport unit for subsequent delivery to the designated location in the mine.
In the chamber, workers also refurbish fastening clamps for connecting the supports, sprags, slings many other small components.
Workers from the material refurbishment and support department with Sebastian Derbis, Manager of Mining Works at KWK Pniówek.

Other news

Future chemists visit CLP-B

Twenty-six students from the Tadeusz Kościuszko Cracow University of Technology came to visit the Central Measurement and Research Laboratory (CLP-B).The students took a close look at modern laboratory equipment.

Modern equipment for rescue workers

Jastrzębska Spółka Węglowa is replacing self rescuer apparatuses in all its mines. This is the largest purchase for mine rescue services in the Company's history.

Methane conference

A two-day workshop on best practices for monitoring, capturing and using methane in coal mines was held in Katowice. The conference was attended by many world experts, including from France, Serbia, China and the United States. Among the speakers was Artur Badylak,…

Occupational health and safety competition for students

The Budryk mine in Ornontowice hosted the finals of the voivodeship occupational health and safety competition for students studying mining professions, entitled "Safe leap from OHS to mining." The competition was organized by the Regional Labor Inspectorate in Katowice…

Serbia: an important trade partner

Jolanta Gruszka, Vice-President of the Management Board for Sales, represented Jastrzębska Spółka Węglowa as part of the government delegation to Serbia. In Belgrade, the representatives discussed opportunities for developing economic cooperation between the countries.

Mobile Flood Protection

JSW Group's Przedsiębiorstwo Budowy Szybów has designed mobile flood barriers as an alternative to solutions such as sandbags and wood barriers. The project is being carried out jointly with the Central Mining Institute and the Łabędy Steelworks.

More news