The Project of Fluidal Block Construction in the Zofiówka CHP Speeds Up

The works on the construction of the CFB70 block, i.e. the largest investment of the JSW Group’s Spółka Energetyczna Jastrzębie, have gathered pace. Such acceleration was necessary to ensure that a new fluidal bed can work at the Zofiówka CHP by the end of 2015.

On 9 December, following an agreement with the technical advisor, another agreement was concluded by Spółka Energetyczna Jastrzębie S.A., i.e. an agreement with the Commercial and Legal Advisor (the consortium of EM&CA and Kancelaria Radcy Prawnego – Małgorzata Szychowska Łódź law firm). The agreements with the advisors make it possible to effectively continue the implementation of the company’s most important investment – the construction of CFB 70MWe fluidal block.

In accordance with the agreement, the commercial and legal advisor is responsible for specifying favourable and lawful provisions to be included in the documentation required in the tender procedure for selection of the General Contractor, as well as ensuring that a utilities contract notice be prepared and duly issued. The commercial and legal advisor will also be actively involved in the entire process of selecting the General Contractor, and will give advice on specifying suitable business solutions and addressing legal and business risks in the contract with the selected General Contractor.

To remind: on 21 October, SEJ already entered into an agreement with ILF Consulting Engineers Polska which has become the company's technical advisor. ILF, in turn, has established cooperation with Energoprojekt Katowice, which has become the project’s subcontractor. “Representatives of both companies are currently carrying out on-site inspections on the premises of SEJ,” says Zbigniew Opałko, project manager of the fluidal block construction. “Detailed analysis of the existing documentation and examination of the facilities located within the plant’s area, will soon make it possible to create, among other things, a construction design, and will also allow us to obtain all necessary building permits and permits for subsequent operation of the block. Until now, ILF has already prepared the wording of a technical part to be contained in the contract notice for the selection of the general contractor,” adds Zbigniew Opałko.

Next year in January, SEJ will launch the public tender for the selection of the General Contractor. The Management Board of SEJ foresees that given the complexity and size of the project, the process of selecting the General Contractor will take at least a few months.

“We expect that we will obtain a final and binding building permit in the middle of the next year, and at the end of the year, the agreement with the General Contractor will be signed,” says the project manager.

The expected date of commencing construction works is scheduled for March 2013. The new fluidal block which will blend with the existing infrastructure, will have been completed by the end of 2015.

Other news

Coking coal at the center of industrial transition

During the 17th European Economic Congress in Katowice, Adam Rozmus, Vice-President of the JSW Management Board for Technical and Operational Matters, spoke in a debate on the future of the mining industry. Panelists discussed, among other things, the place of coking…

Shaft sinking completed at Zofiówka

The sinking of shaft IIz to a depth of 1,104.68 meters has been completed at the Borynia-Zofiówka-Bzie mine in the Zofiówka Section. This is a very important project for the mine from the point of view of building the new 1,080 level.

Polish Cup returns to JSW Jastrzębski Węgiel

After a 15-year hiatus, the volleyball players once again took the TAURON Polish Cup, defeating Aluron CMC Warta Zawiercie 3:1 in the final in Kraków. After the great success, the team appeared with the trophy at the headquarters of JSW, the title sponsor, where they…

JSW SA has applied to the Ministry of Climate and Environment for a refund of the windfall tax

On Friday, 11 April 2025, JSW SA requested a refund of the windfall tax of PLN 1.6 billion paid in 2023 and surcharged in 2024. This is the result of a thorough analysis of the regulations that imposed the obligation to pay this levy on the Company.

Budryk Mine hosted the best students of mining schools

Promoting a culture of safety among young people, educating about labor law and OHS principles, as well as drawing attention to the importance of mining for the region and the economy - these are the main goals of the competition entitled "Safe Step to Mining with OHS",…

New longwalls in Pniówek mine

Two new longwalls with total reserves of approx. 1.4 million tons of coking coal with very good parameters have been put into operation at the Pniówek mine.

More news